Week 28, Day 1

Week 28, Day 1:

  • Some rain showers through the day, hence the spots on the camera lens and applying the oil to the cedar boards had to move inside
  • More electrical first-fix
  • Installing the ALUTRIX membrane over the black primer on the underside of the roof, and priming the areas not done on Friday
Week 28, Day 1

Week 28, Day 1

Plenty of room to work indoors when it's raining

Plenty of room to work indoors when it’s raining

Power, data and a light switch at both sides of the bed in the Master Bedroom

Power, data and a light switch at both sides of the bed in the Master Bedroom

ALUTRIX 600 membrane on the store cupboard for Bedroom 5

ALUTRIX 600 membrane on the store cupboard for Bedroom 5