Week 25, Day 5

Week 25, Day 5:

  • Preparation for the concrete slab on the ground floor
  • Floor insulation and damp-proof membrane
  • First-fix plumbing and electrical installations for the kitchen island
Week 25, Day 5

Week 25, Day 5

Insulation above beam-and-block floor and below concrete floor slab

Insulation above beam-and-block floor and below concrete floor slab

The insulation is 250mm thick: 100 + 50 + 100 of Celotex / Reticel boards.

First-fix Plumbing in Kitchen

First-fix Plumbing in Kitchen

Steel reinforcing mesh for concrete floor slab

Steel reinforcing mesh for concrete floor slab