  • A working Saturday, completing the installation of the plywood boxes for the external doors and tidying up the beam-and-block floor in preparation for the insulation and the concrete floor slab
Week 24, Day 6

Week 24, Day 6

Completed plywood box for side door

Completed plywood box for side door

IMG_1755

Completed plywood boxes for lift-and-slide doors

Beam-and-block floor in Living Room

Beam-and-block floor in Living Room

The dark blocks are replacements for ones that had cracked.