Week 27, Day 4

Week 27, Day 4:

  • Still more first-fix
  • Starting to install the black membrane that goes over the outer skin of block-work (and over the insulation on the outside of the SIPs on the gable walls), together with the vertical timber battens that will hold the horizontal cedar boards over the first- and second-floor walls
Week 27, Day 4

Week 27, Day 4

Black membrane and vertical battens on east wall

Black membrane and vertical battens on east wall

Close-up of membrane and vertical battens