Week 29, Day 5

Week 29, Day 5:

  • More first-fixing, completing the intruder and fire alarm system and progressing the electrical installation
  • Preparing the second floor for plasterboard, with air-tight membranes and battens on the walls
Week 29, Day 5

Week 29, Day 5

Pro Clima Kaflex air-tight cable grommet sealing alarm cable connection to external bell box

Pro Clima Kaflex air-tight cable grommet sealing alarm cable connection to external bell box

Second floor bathroom ready for plasterboard

Second floor bathroom ready for plasterboard

Week 29, Day 4

Week 29, Day 4:

  • More first-fix: electrical, plumbing and alarms
  • More preparation for plaster on the first and second floors
Week 29, Day 4

Week 29, Day 4

FIrst-fix of the low-loss header feeding the three heating circuits via Honeywell zone valves and Grundfos Alpha2 pumps

FIrst-fix of the low-loss header in the Plant Room, feeding the three heating circuits via Honeywell zone valves and Grundfos Alpha2 pumps