Week 29, Day 5

Week 29, Day 5:

  • More first-fixing, completing the intruder and fire alarm system and progressing the electrical installation
  • Preparing the second floor for plasterboard, with air-tight membranes and battens on the walls
Week 29, Day 5

Week 29, Day 5

Pro Clima Kaflex air-tight cable grommet sealing alarm cable connection to external bell box

Pro Clima Kaflex air-tight cable grommet sealing alarm cable connection to external bell box

Second floor bathroom ready for plasterboard

Second floor bathroom ready for plasterboard