Week 31, Day 3

Week 31, Day 3:

  • Wet diamond-grinding the concrete floor, taking off 1-2mm to remove the crazing on the top surface and exposing some of the sand grains (see tomorrow for a photo)
  • Completing the timber cladding on the eastern elevation
  • More progress on the plastering, mainly in the Plant Room
Week 31, Day 3

Week 31, Day 3

Timber cladding completed on the east elevation

Timber cladding completed on the east elevation

Skim coat of plaster over the FireLine boards in the Plant Room

Skim coat of plaster over the FireLine boards in the Plant Room