Week 30, Day 5

Week 30, Day 5:

  • As usual these days, more first-fix of the electrical and plumbing systems
  • A site meeting with the lighting designer to finalize the design for the second floor lighting where we’re having to use low-profile and surface-mount fittings because there’s only a shallow service void between the plasterboard and the SIPs
  • Work preparing for the wet plaster on the masonry walls, applying pro clima Contega PV tape on the edges of the plywood boxes for the windows
    • This has a mesh component which embeds in the plaster and a fleecy component which also sticks to the plaster and provides an air seal
  • A delivery of semi-rigid pipes for the ventilation system
Week 30, Day 5

Week 30, Day 5

Air tightness tape (pro clima Contega PV) where window boxes meet masonry walls

Air tightness tape (pro clima Contega PV) where window boxes meet masonry walls

MVHR ductwork ready for installation

MVHR ductwork ready for installation