Week 30, Day 3:
- Delivery of the lighting fixtures required for first-fix, where they need to be incorporated into the plaster on the walls or ceilings
- More electrical first-fix, including cabling the control points for the electric windows and blinds
- More plumbing first-fix, including installing the pipework for the bath fillers and the digital shower control boxes