Week 32, Day 1

Week 32, Day 1:

  • Some showers at the end of the day, hence the rain-spots on the lens of the time-lapse camera
  • Good progress installing the majority of the ventilation ducts back to the plenum chambers in the Plant Room
  • Some preparatory work by Western Power Distribution for upgrading and re-routing the electricity supply cable from the transformer – they will be installing a larger cable and burying it underground