Week 31, Day 3

Week 31, Day 3:

  • Wet diamond-grinding the concrete floor, taking off 1-2mm to remove the crazing on the top surface and exposing some of the sand grains (see tomorrow for a photo)
  • Completing the timber cladding on the eastern elevation
  • More progress on the plastering, mainly in the Plant Room
Week 31, Day 3

Week 31, Day 3

Timber cladding completed on the east elevation

Timber cladding completed on the east elevation

Skim coat of plaster over the FireLine boards in the Plant Room

Skim coat of plaster over the FireLine boards in the Plant Room

Week 31, Day 2

Week 31, Day 2:

  • More first-fix
  • Routing some of the semi-rigid ventilation ducts for the MVHR system, relatively easy using the plastic ducts and with the Easi-Joists but still something of a challenge in the more congested areas
Week 31, Day 2

Week 31, Day 2

All the ventilation ducts need to pass through the Second Bedroom ceiling

All the ventilation ducts need to pass through the Second Bedroom ceiling

Some of the rooms require twin ducts to carry the required flow rate

Some of the rooms require twin ducts to carry the required flow rate