Week 41, Day 3

Week 41, Day 3:

  • I’ve probably not done the continued good progress on the plastering justice in recent posts so there’s a photo of the Living Room nearing completion
  • The ceiling of the balcony has been insulated, including the steel beams
  • The kitchen is progressing, with all the drawers now installed
  • More second-fix electrical and plumbing
Week 41, Day 3

Week 41, Day 3

Plastering in the Living Room

Plastering in the Living Room

Insulation over balcony

Insulation over balcony

Kitchen units almost ready for appliances

Kitchen units almost ready for appliances

Week 41, Day 2

Week 41, Day 2:

  • Quite a busy day – the 16:00 time-lapse snapshot caught one of the solar panels being installed
    • The 18 panels and the inverter are now Installed but not Commissioned
  • Installation of the first batch of oak flooring, in the Home Office on the Second Floor
  • More work on the kitchen installation
  • More plastering and second-fix electrical
  • Slightly re-working the membrane roof covering for the balcony floor to make sure any water drains properly
Week 41, Day 2

Week 41, Day 2

Support frames for Solar PV panels installed, clamped to standing seams on zinc roofing

Support frames for Solar PV panels installed, clamped to standing seams on zinc roofing

View from main camera location with Solar PV panels installed

View from main camera location with Solar PV panels installed

SolarEdge inverter installed in Plant Room

SolarEdge inverter installed in Plant Room

Oak flooring installed in Office on Second Floor

Oak flooring installed in Office on Second Floor

Second day of kitchen installation

Second day of kitchen installation