Week 39, Day 5:
- The engineered oak wood flooring boards were delivered – these will be left to acclimatise inside the house before being installed
- The Sika Sarnafil single-ply roofing membrane was installed on the first-floor balcony by Derwent Roofing Services
- The computer network patch panel installation was completed
- More work on the plastering
- More work on the electrical second-fix
- More work on the zinc roofing, completing some of the fiddly work around the eaves and the soffits