Week 38, Day 4

Week 38, Day 4:

  • Another day with a significant change visible from the time-lapse camera – the standing-seam zinc roof covering has started going on the south roof
  • Second-fix has started for the electrical installation, with mains sockets now installed on the second floor and the 9u, 19″ communications equipment rack mounted on the wall in the Comms Room on the second floor
  • More wet plastering, aiming to get the bathrooms ready for sanitaryware and tiling next week