Week 40, Day 4

Week 40, Day 4:

  • Floor tiling in the bathrooms – the tiles are now installed in about half of the rooms
  • Delivery of the appliances for the kitchen ready for those to be installed next week
  • Tidying up the external corners on the cedar cladding
  • More plastering in the ground-floor rooms
  • More second-fix electrical, preparing some of the connections in the Plant Room
    • There’s now power to some of the circuits, including the PIR-switched lights in the Plant, Comms and Storage Rooms on the Second Floor
Week 40, Day 4

Week 40, Day 4

Floor tiles (without grout yet) in the Second-Floor Bathroom

Floor tiles (without grout yet) in the Second-Floor Bathroom

Floor tiling (without grout yet) in the En-Suite for Bedroom 3

Floor tiling (without grout yet) in the En-Suite for Bedroom 3

Finishing touches to the cedar cladding at the external corners

Finishing touches to the cedar cladding at the external corners