Week 38, Day 3

Week 38, Day 3:

  • The first change in the outside view for a while – the team from Full Metal Roofing are back on site and have been working on the south roof
    • After lots of discussion the agreement is to install a “structured underlay” under the zinc sheets on both the north and south roof
    • This underlay has a springy plastic mesh which creates an air space between the zinc and the supporting OSB, allowing for a degree of ventilation and importantly letting any condensation which might form under the zinc drain away
  • More plastering, more electrical first-fix and more door frames
  • Installing the recessed LED strip light in the entrance hall
Week 38, Day 3

Week 38, Day 3

RHEINZINK VAPOZINC structured underlay and galvanized steel reinforcing straps on the south roof

RHEINZINK VAPOZINC structured underlay and galvanized steel reinforcing straps on the south roof

Circuit breaker boards in the cupboard on the ground floor

Circuit breaker boards in the cupboard on the ground floor

Recessed strip light in ground floor hallway

Recessed strip light in ground floor hallway