Week 40, Day 1

Week 40, Day 1:

  • Installing the painted aluminium channels over the wooden posts between the clerestory windows and also the aluminium window cills, now the zinc roofing has been completed at the top of the south roof
  • More work on the zinc roofing – the fiddly bits around the edges take much longer than the large flat areas
  • More plastering, mainly in the open plan kitchen – getting that ready for the kitchen units (due next week)
  • Making up some corner caps out of cedar boards to finish off the external corners on the cedar-clad areas
Week 40, Day 1

Week 40, Day 1

Aluminium channels over insulation covering the posts between the clerestory windows

Aluminium channels over insulation covering the posts between the clerestory windows

Skimmed plasterboard ceiling in kitchen

Skimmed plasterboard ceiling in kitchen

Fabricating caps for the external corners on the cedar-clad areas

Fabricating caps for the external corners on the cedar-clad areas