Week 37, Day 5

Week 37, Day 5:

  • More plastering
  • A bit of plumbing first-fix
  • More electrical first-fix, mainly sockets and the ceiling lights on the ground floor
Week 37, Day 5

Week 37, Day 5

Recessed plaster downlight housings in kitchen

Recessed plaster downlight housings in kitchen

Finished dropped ceiling in Bedroom 2 En-Suite