Week 41, Day 1

Week 41, Day 1:

  • The last section of zinc roofing on the south roof got completed, ready for the Solar PV installation (tomorrow)
  • The kitchen units were delivered, unpacked and roughly positioned
  • More second-fix plumbing, taking delivery of the remaining basins and toilets and installing some more of the basins
  • More second-fix electrical, mainly in the Plant Room
Week 41, Day 1

Week 41, Day 1

Kitchen unit delivery

Kitchen unit delivery

Kitchen island units and sink units beyond

Kitchen island units and sink units beyond

Basin in En-Suite for Bedroom 3

Basin in En-Suite for Bedroom 3

Week 40, Day 5

Week 40, Day 5:

  • Completion of the floor tiling in all but the Ground Floor shower room, grouting the tiles installed yesterday
  • Clearing out the Living Room which had been used as a workshop, in readiness for plastering – and then dry-lining the wall with the back-plate for the cantilevered staircase
Week 40, Day 5

Week 40, Day 5

Grouted floor tiles in the Master Bedroom En-Suite

Grouted floor tiles in the Master Bedroom En-Suite

Grouted floor tiles in the Master Bedroom En-Suite

Grouted floor tiles in the Master Bedroom En-Suite

Dry lining over staircase back-plate in the Living Room

Dry lining over staircase back-plate in the Living Room