Week 7, Day 2

Week 7, Day 2:

  • Very good progress installing almost all of the concrete floor beams and roughly 40% of the dark grey 3.6N infill blocks. Stronger (7.3N) blocks are required in some areas, wherever a wall will be supported by the floor structure.
Week 7, Day 2

Week 7, Day 2

Week 7, Day 1

Week 7, Day 1:

  • Completion of the last bit of below-ground blockwork walling
  • Laying of the oversite concrete in all but the two smallest rooms
Week 7, Day 1

Week 7, Day 1

Oversite concrete being poured

Oversite concrete being poured

Mostly-completed oversite concrete at the end of Week 7, Day 1 - just the Shower Room and Utility Room left to complete

Mostly-completed oversite concrete at the end of Week 7, Day 1 – just the Shower Room and Utility Room left to complete