Week 30, Day 4

Week 30, Day 4:

  • More first-fixing
  • Plastering-in the air-tight tape on the southern bedroom walls, where these will get plasterboard rather than a wet plaster finish (which normally forms the air-tight layer)
  • More work on the studwork walls – especially on the second floor where the plasterboard will get installed first
Week 30, Day 4

Week 30, Day 4

Air-tight tape now plastered into place in master bedroom

Air-tight tape now plastered into place in master bedroom

Studwork wall in second floor bathroom

Studwork wall in second floor bathroom

Week 30, Day 3

Week 30, Day 3:

  • Delivery of the lighting fixtures required for first-fix, where they need to be incorporated into the plaster on the walls or ceilings
  • More electrical first-fix, including cabling the control points for the electric windows and blinds
  • More plumbing first-fix, including installing the pipework for the bath fillers and the digital shower control boxes
Week 30, Day 3

Week 30, Day 3

First-fix wiring for electric windows and blinds

First-fix wiring for electric windows and blinds

Mira Platinum digital shower mixers

Mira Platinum digital shower mixers